Electrification project in Labatinngyi village in Thandaunggyi Township completed

Thandaunggyi 17 February

 

Electrification project is being undertaken in Labatinngyi village in Thandaunggyi Township, Hpa-an District, Kayin State during six month budget. Now, the project has been completed by hundred percent, according to Township Department of Rural Development.  

 

The project including installation of power line and transformer was conducted with K 10 million funded by VDP and K 3.5 million contributed by local people with the technical aids of Township Electricity Supply Enterprise. 

 

The project was conducted starting from first week of December, 2021 and now, it has been completed by hundred percent. Upon completion, a total of 650 people from 150 households in the village will be available 24-hour electricity. 


Than Lwin (Magway)
Translated by Suyee