RELEVANT officials conducted a field inspection yesterday of the construction of a retaining wall beside the multi-purpose hall in Sipinhla Village, Sinbaungwe Township, Magway Region, which is being carried out using the Model Village Project-approved budget and public community contributions for the 2026-2027 financial year.
Acting Township Head Daw Ei Ei Mon of the Sinbaungwe Township Department of Rural Development, along with officials and members of the Model Village Project Committee, inspected the retaining wall construction. The acting township head instructed those involved to complete the work on time and adhere strictly to the specified design standards and schedules.
The retaining wall in Sipinhla Village is 90 feet long, three feet and six inches wide, and seven feet and six inches high. It is being implemented by the villagers themselves with technical assistance from engineers of the Department of Rural Development, utilizing an approved Model Village project budget of K10 million and community public contributions of K0.95 million, totalling K10.95 million for the 2026-2027 financial year.
Construction began in the third week of September this year and has now reached 70 per cent completion. Once fully completed, the project will benefit 626 people from 171 households in the village, according to Daw Ei Ei Mon, Acting Township Head of the Sinbaungwe Township Department of Rural Development. — Nyein Thu (DRD)