THE concrete paving of an internal road in Gwaypin Village, Ywathagyi Village-tract, executed by the Myaungmya Township Department of Rural Development under the Ministry of Cooperatives and Rural Development (Ayeyawady Region) using the Village Development Project (VDP) grant for the 2026-2027 fiscal year alongside local community contributions, has now been 100 per cent completed after starting in the first week of August.
The concrete road project—measuring 332 feet in length, 10 feet and six inches in width, and six inches in thickness—was funded with K15 million from the VDP grant and K5 million contributed by local villagers, totaling K 20 million.
Under the close supervision of Township Department of Rural Development staff, the villagers themselves implemented the project starting from August, according to U Thet Paing Oo, Staff Officer (Technical) of the Myaungmya Township Department of Rural Development.
Yesterday morning, Staff Officer (Technical) U Thet Paing Oo and department staff, together with members of the Village Development Committee, inspected the completed concrete road construction work and discussed necessary operational matters. — Than Lwin (Magway)