Officials from Daik-U Township Department of Rural Development made a field trip on 16 November to observe the progress of village development works in Laekyamyaung village, Sitbogyi village-tract in the township, Nyaunglaybin District, Bago Region.
During the trip, officials from the township department accompanied by members of village development committee inspected the completion of the gravel road construction and water treatment plant installation, urging the relevant people to ensure the sustainable maintenance.
The road measuring 845 ft in length, 12 ft in width and six inches in thickness and the water treatment plant capable of treating over 200 gallons of water per hour were conducted with K 15 million of VDP funds and K 1.06 million of public contributions under the guidance of the departmental personnel. The project began on 8 October and has now been fully completed. Once completed, a total of 667 people from 129 households are now using the water treatment plant, according to an official.